In our Sanctioned Projects under Municipal Solid Waste, M/s. SELCO INTERNATIONAL LTD have commissioned. |
|
| |
More |
|
|
|
 |
|
 |
|
|
|
|
|
| |
|
| Municipal Waste Power Projects |
Status of projects sanctioned under municipal solid waste as on 31.03.2008
Municipal Waste based Power projects Commissioned |
Sl.
No |
Name of the Developer |
Capacity |
Location |
Type of waste |
Date of Sanction |
Status |
Whether sale to DISCOM / Captive use |
| I. MAHABOOBNAGAR |
| 1. |
M/s Selco International Ltd., Hyderabad. |
6.6 MW |
Elikatta (V), MBNR Dist. |
MSW |
5-6-2000 |
Commissioned
On 8.11.2003 |
Sale to DISCOM |
| II. KRISHNA |
| 2. |
M/s. Sri Ram Energy Systems Ltd., Hyderabad |
6.0 MW |
Vijayawada |
By utilizing Solid wastes of Vijayawada & Guntur |
30-12-02 |
Commissioned
On 4.12.2003 |
Sale to DISCOM |
| 3. |
Vijayawada Municipal Corporation Biomethanation plant, Vijayawada |
3255
KW /per
Day.
(0.15 MW) |
Vijayawada |
By utilizing Vegetable market waste |
28-02-04 |
Commissioned on 11th November-2004 |
Sale to DISCOM |
| |
Total |
12.75 MW |
|
|
|
|
|
|
|
| Municipal waste based projects under Implementation |
Sl.
No. |
Name of the Developer |
Capacity |
Location |
Type of waste |
Date of Sanction |
Status |
| 1. Nalgonda District |
| 1 |
M/s. R.D.F power projects Ltd,
Hyderabad. |
11.0 MW |
Chinnaravulapally (V), Bibinagar (M), Nalgonda District. |
MSW |
Original sanctioned dt.16.6.2000
Revival of the Project
on
02.02.2005 |
PPA entered with TATA Power Trading Co, Mumbai |
| 2. Visakhapatnam District: |
| 2 |
M/s. Visakha Energy systems Ltd |
6.6 MW |
Kapulu-pada (V)
Bhimili (M)
Visakhapatnam (Dt) |
MSW |
11.3.2005 |
PPA not entered |
| 3. |
M/s. Shalivaha Projects Ltd., Secunderabad |
7.6 MW |
Rebaladevpally Village, Sulthanabad Mandal, Karimnagar District |
MSW |
18.9.2007 |
PPA entered with TATA Electric Supply Co. |
| |
Total |
25.2 MW |
|
|
|
|
|
|
| Abstract |
| Sl.No |
Description |
No. of Projects |
Capacity |
| 1 |
Sanctioned |
6 |
37.95 MW |
| 2 |
Commissioned |
3 |
12.75 MW |
| 3 |
Under implementation (PPA not entered) |
3 |
25.2 MW |
|
|
|
|
|
|
|
|